GPL narrows down fault at Canefield Substation as restoration works continue

The Guyana Power and Light Inc. (GPL) has narrowed down the fault responsible for the prolonged electricity outage affecting customers across Berbice to the grounding transformer panel at the Canefield Substation.
In an update on Saturday, the company said its technical teams have been working around the clock since Thursday evening to identify and address the problem, following the development at the substation.
GPL said extensive troubleshooting was conducted, including inspections of the wiring, electrical panels, busbar and distribution feeders. During those exercises, several faulty components were identified and replaced.
However, following further testing and assessments, technicians were able to narrow down the fault to the grounding transformer panel.
The company said work is currently underway to replace several defective components, after which additional testing will be conducted to facilitate the safe restoration of electricity supply.
The restoration exercise is being led by GPL’s Deputy Chief Executive Officer of Strategic Operations, Bharat Harjohn, and Divisional Director of Transmission and Distribution, Shaun Hamlet, with technical assistance from Kalpataru Projects International Limited.

GPL’s management team is also overseeing the ongoing operations, which the company said will continue around the clock until the outstanding technical issues are addressed.
Meanwhile, the company has apologised to residents and businesses across Berbice for the prolonged interruption, acknowledging the frustration, inconvenience and hardship being experienced by affected customers.
GPL said an estimated restoration time will be communicated in a subsequent update, while assuring customers that every effort is being made to resolve the situation as safely and quickly as possible.